Cubic metres before anything else
Feed the sub-base calculator the footprint and the compacted depth. A 6 m by 3 m garage base with 150 mm of hardcore under it works out at 18 m² of sub-base, 2.7 m³ dug and muck-away, and roughly 5.4 tonnes delivered if the stone compacts at 2.0 t/m³. Quarry's density differs? Overwrite it.
Tick the lines you want and they're added at your own rates. An area calculator measures awkward footprints into a priced m² line.